S.No. |
PERSON |
ENTITY |
REGULATORY CHARGES |
REGULATORY ACTION(S) / DATE OF ORDER |
FURTHER DEVELOPMENTS |
1 |
|
ANIL DHIRAJLAL AMBANI
|
|
|
RELIANCE INFRASTRUCTURE LTD.
|
|
ALLEGED AMOUNTS RAISED TOWARDS EXTERNAL COMMERCIAL BORROWINGS (ECBS)/FOREIGN CURRENCY CONVERTIBLE BONDS(FCCBS) BY ADA GROUP COMPANIES UTILISED TO INVEST IN SCRIP OF RELIANCE COMMUNICATIONS LTD.
|
REACHED SETTLEMENT (SETTLEMENT CHARGES RS.25,00,00,000 ALONG WITH OTHER ENTITIES/PERSONS VIDE CONSENT ORDER)
REACHED SETTLEMENT (CONSENT ORDER) (AGREED VOLUNTARILY NOT TO INVEST IN LISTED SECURITIES (OTHER THAN MUTUAL FUND)) FROM 14-JAN-2011 TO 31-DEC-2011
14-JAN-2011
|
|
2 |
|
ANIL DHIRAJLAL AMBANI
|
|
|
RELIANCE NATURAL RESOURCES LTD.
|
|
ALLEGED AMOUNTS RAISED TOWARDS EXTERNAL COMMERCIAL BORROWINGS (ECBS)/FOREIGN CURRENCY CONVERTIBLE BONDS(FCCBS) BY ADA GROUP COMPANIES UTILISED TO INVEST IN SCRIP OF RELIANCE COMMUNICATIONS LTD.
|
REACHED SETTLEMENT (SETTLEMENT CHARGES RS.25,00,00,000 ALONG WITH OTHER ENTITIES/PERSONS VIDE CONSENT ORDER)
REACHED SETTLEMENT (CONSENT ORDER) (AGREED VOLUNTARILY NOT TO INVEST IN LISTED SECURITIES (OTHER THAN MUTUAL FUND)) FROM 14-JAN-2011 TO 31-DEC-2011
14-JAN-2011
|
|
3 |
|
J.P.CHALASANI
|
|
|
RELIANCE INFRASTRUCTURE LTD.
|
|
ALLEGED AMOUNTS RAISED TOWARDS EXTERNAL COMMERCIAL BORROWINGS (ECBS)/FOREIGN CURRENCY CONVERTIBLE BONDS(FCCBS) BY ADA GROUP COMPANIES UTILISED TO INVEST IN SCRIP OF RELIANCE COMMUNICATIONS LTD.
|
REACHED SETTLEMENT (SETTLEMENT CHARGES RS.25,00,00,000 ALONG WITH OTHER ENTITIES/PERSONS VIDE CONSENT ORDER)
REACHED SETTLEMENT (CONSENT ORDER) (AGREED VOLUNTARILY NOT TO INVEST IN LISTED SECURITIES (OTHER THAN MUTUAL FUND)) FROM 14-JAN-2011 TO 31-DEC-2011
14-JAN-2011
|
|
4 |
|
LALIT JALAN
|
|
|
RELIANCE INFRASTRUCTURE LTD.
|
|
ALLEGED AMOUNTS RAISED TOWARDS EXTERNAL COMMERCIAL BORROWINGS (ECBS)/FOREIGN CURRENCY CONVERTIBLE BONDS(FCCBS) BY ADA GROUP COMPANIES UTILISED TO INVEST IN SCRIP OF RELIANCE COMMUNICATIONS LTD.
|
REACHED SETTLEMENT (SETTLEMENT CHARGES RS.25,00,00,000 ALONG WITH OTHER ENTITIES/PERSONS VIDE CONSENT ORDER)
REACHED SETTLEMENT (CONSENT ORDER) (AGREED VOLUNTARILY NOT TO INVEST IN LISTED SECURITIES (OTHER THAN MUTUAL FUND)) FROM 14-JAN-2011 TO 31-DEC-2011
14-JAN-2011
|
|
5 |
|
S.C.GUPTA
|
|
|
RELIANCE INFRASTRUCTURE LTD.
|
|
ALLEGED AMOUNTS RAISED TOWARDS EXTERNAL COMMERCIAL BORROWINGS (ECBS)/FOREIGN CURRENCY CONVERTIBLE BONDS(FCCBS) BY ADA GROUP COMPANIES UTILISED TO INVEST IN SCRIP OF RELIANCE COMMUNICATIONS LTD.
|
REACHED SETTLEMENT (SETTLEMENT CHARGES RS.25,00,00,000 ALONG WITH OTHER ENTITIES/PERSONS VIDE CONSENT ORDER)
REACHED SETTLEMENT (CONSENT ORDER) (AGREED VOLUNTARILY NOT TO INVEST IN LISTED SECURITIES (OTHER THAN MUTUAL FUND)) FROM 14-JAN-2011 TO 31-DEC-2011
14-JAN-2011
|
|
6 |
|
SATISH SETH
|
|
|
RELIANCE INFRASTRUCTURE LTD.
|
|
ALLEGED AMOUNTS RAISED TOWARDS EXTERNAL COMMERCIAL BORROWINGS (ECBS)/FOREIGN CURRENCY CONVERTIBLE BONDS(FCCBS) BY ADA GROUP COMPANIES UTILISED TO INVEST IN SCRIP OF RELIANCE COMMUNICATIONS LTD.
|
REACHED SETTLEMENT (SETTLEMENT CHARGES RS.25,00,00,000 ALONG WITH OTHER ENTITIES/PERSONS VIDE CONSENT ORDER)
REACHED SETTLEMENT (CONSENT ORDER) (AGREED VOLUNTARILY NOT TO INVEST IN LISTED SECURITIES (OTHER THAN MUTUAL FUND)) FROM 14-JAN-2011 TO 31-DEC-2011
14-JAN-2011
|
|
The regulatory charges/regulatory actions may be fully or partly applicable to the entities/persons mentioned in the second column. |